Project
Glass window safety film installation at Millennium Point, Birmingham
Millennium Point is a landmark building in the centre of Birmingham. Like many building facades consisting of a large expanse of toughened glass, spontaneous breakage due to Nickel Sulphide Inclusions...
Birmingham
Commercial
Safety Window Film
Completed 2 weeks ahead of schedule (May to late August 2017)
the challenge
Landmark building in Birmingham with a large expanse of toughened glass was experiencing spontaneous breakage due to Nickel Sulphide Inclusions, posing a risk of injury to personnel below.
our solution
Applied Solar Gard Sentinel Plus 100 Micron Clear (OSW) external weatherable safety film combined with a structural silicone edge attachment system to contain glass fragments in the event of breakage.

measurable impact
the strategic results delivered through our technical implementation
project details
Millennium Point is a landmark building in the centre of Birmingham. Like many building facades consisting of a large expanse of toughened glass, spontaneous breakage due to Nickel Sulphide Inclusions had become a health and safety issue. Over time several of the building's window panes had spontaneously shattered placing personnel below at risk of injury. It was time for decisive action.
The building owners contacted Lustalux in late 2016 and asked us to tender for the work which would involve applying an external grade clear safety film in conjunction with a structural silicone edge attachment system. After several meetings between ourselves, the client and our principal window film manufacturer Saint-Gobain Solar Gard, Millennium Point awarded Lustalux the contract to fulfil the project. Solar Gard's Sentinel Plus 100 Micron Clear (OSW) Outside Weatherable Safety Film was chosen for its durability and ability to easily contain glass fragments in the event of breakage.
The work began in May 2017 and was scheduled to be completed by early September however due to the skills of our operatives, a helpful client and fair weather we finished two weeks ahead of schedule in late August.
In all, almost four thousand square metres of glass was treated including a large expanse from fixed scaffolding behind Brise Soleil louvres - not a straight forward application by any means. The rest of the work was carried out using powered scissor lifts and booms, most of it while the building was in full operation. Further testament to our working practices and safe operating credentials.
key outcomes
- Treatment of almost 4,000 square metres of glass.
- Project completed two weeks ahead of schedule.
- Work performed using powered scissor lifts and booms while the building was operational.
- Included difficult application behind Brise Soleil louvres.
our approach
Tender & Selection
Detailed meetings with client and Saint-Gobain Solar Gard to select the optimal safety film.
Phased Installation
Use of powered access equipment and scaffolding to treat all glass elevations safely.
Quality Assurance
Edge sealing with Dow Corning architectural silicone for long-term durability.
project faqs
Q: What causes spontaneous breakage?
Nickel Sulphide Inclusions in toughened glass can expand over time, causing the pane to shatter without warning.
Q: Can film be applied while the building is in use?
Yes, our team is experienced in working safely around building occupants using specialized access equipment.