Project
ACC Liverpool — Internal Refurbishment
Architectural-film refurbishment of ten existing facility areas at ACC Liverpool, programmed around the venue's events calendar.
project details
- Location
- Liverpool
- Sector
- Events & hospitality
- Timeline
- 4 weeks, with individual areas completed in 1–2 days
the challenge
ACC Liverpool needed ten existing toilet blocks refreshed without the programme and disruption associated with removing structurally sound cubicle systems. Work had to be completed around a busy events calendar.
our solution
Lustalux retained the existing cubicle structures and resurfaced them with architectural film in phases. Approximately 1,500 metres of LG architectural film (now LX Hausys) was installed over a four-week programme, with individual areas completed in approximately 1–2 days.
measurable impact
the strategic results delivered through our technical implementation
key outcomes
- Ten existing toilet blocks refreshed by resurfacing the cubicle structures rather than replacing them.
- Approximately 1,500 metres of architectural film installed over a four-week programme.
- Each area completed in approximately 1–2 days so that other facilities could remain available.
- Installation planned around the venue's events calendar, with the Lustalux team operating as a self-contained package.
project details
ACC Liverpool needed ten existing toilet blocks refreshed without removing cubicle systems that were still structurally sound. After comparing a full refit with resurfacing, the venue specified interior architectural film.
Lustalux was on site for four weeks installing approximately 1,500 metres of LG architectural film (now LX Hausys) to the dated cubicles. Rather than a full strip-out, the existing panels were prepared and wrapped in a modern finish, with each area completed in approximately 1–2 days around the convention centre's events calendar.
“We’ve been open since 2008 and the toilets were starting to look quite dated. Initially, we had the idea of renovating the whole toilet, which includes ripping everything out to fit brand new toilet cubicles and panels. After a bit of investigation, we discovered that was going to be quite costly, and with the panels being in pretty good condition, we approached Lustalux for a more cost-effective option.” — Zak Khachik, Head of Operations, ACC Liverpool
To install the film, the team sanded and cleaned the panels, then applied the film directly to the retained substrate.
“Lustalux has been really good from quotation right through to project management. We are a busy convention centre, and it was great that Lustalux could work around us, whilst being self-contained and keeping noise to a minimum.” — Zak Khachik, Head of Operations, ACC Liverpool
The recorded 75% saving compared with cubicle replacement belongs to this ACC Liverpool specification. It is not a universal architectural-film cost, waste or downtime claim. For commercial architectural film, window film and signage across Liverpool and Merseyside, see Liverpool architectural film.
our approach
Preparation
Existing panels were sanded and cleaned so the film could be applied to the retained cubicle structures.
Phased install
Each bathroom block was completed in approximately 1–2 days to keep facility availability during the events programme.
Venue coordination
The install was programmed around ACC Liverpool's calendar, with the site team describing Lustalux as self-contained and needing little venue input.
project faqs
Q: Why use film instead of new cubicles?
At ACC Liverpool the existing panels were in serviceable condition, so resurfacing them avoided a full rip-out. That reduced programme length and waste compared with replacing the cubicles. Suitability still depends on the substrate on each project.
Q: How long did the installation take?
Each bathroom block was completed in approximately 1–2 days, and the ten-block programme ran over four weeks around the venue's events calendar.
project gallery





related projects
view all
Red Bull Harbour Reach Branding Case Study
Historic event graphics for Red Bull Harbour Reach at Liverpool's Albert Dock — vinyl wraps and branding on wakeboarding ramps and obstacles in a wet marine environment.

Everton Stadium at Bramley-Moore Dock
Glass manifestation applied to newly glazed openings in the hydraulic engine house at Bramley-Moore Dock, Liverpool, within a main-contractor and architectural-glazing package.

Grand Junction Retail Park — Facade Refresh
Exterior wrapping film facelift to improve finish and longevity—without replacement disruption.
have a similar project in mind
discuss your requirements with a specialist and get a tailored quote for your space